Timelines and Estimates

Production Timelines

Precision timber frame building requires appropriate planning and execution time, which usually takes from 14 to 18 weeks prior to delivery of the frame to a building site.

The following provides estimated turn-around on required stages of work:

  • Final engineering:   2 – 4 weeks
  • Material milling from log to timber:  4 weeks
  • Kiln drying to stabilize timber:  4 weeks
  • Timber frame fabrication:  2 – 4 weeks
  • Finishing:  2 weeks
production timeline

Project Estimates

Daizen develops estimates based on the unique requirements of each project taking into account the type and size of materials chosen, proportions, custom finishes and accessories. With this variability, we quote based on the volume of wood in board/feet units. We provide every client the opportunity to review the budget prior to beginning work so expectations and costs are well understood.